Total Engineering

PLC Labbeta

Ladder program

① Leer entradas② Ejecutar rungs③ Escribir salidas

Tap a cell to choose the instruction, or pick a tool above and tap the cells.

Challenges

Each challenge checks itself: the lab tests your program with a sequence of button presses and checks the outputs. Your progress is saved in this browser.

Help

How to edit the diagram
Addresses
Instructions
Scan cycle

In RUN, the PLC repeats three steps non-stop: 1) it copies the state of every input into the process image, 2) it executes the rungs from top to bottom using that image and 3) it writes the outputs. Here each scan lasts 10 simulated ms. If a coil appears in two rungs, the last one executed wins. In STOP all outputs turn off, and on returning to RUN the markers, timers and counters are cleared. Use “1 scan” in STOP to step one cycle at a time.

What you can learn here

What a PLC is

A PLC (programmable logic controller) is an industrial computer that reads sensors and push buttons, runs a program and drives contactors, valves and pilot lights. It replaced relay panels because it can be reprogrammed without rewiring. You’ll find it in packaging plants, mining, water pumping, lifts and almost any automatic machine.

Ladder diagram

Ladder logic (LD in the IEC 61131-3 standard) draws the program like a relay wiring diagram: two vertical rails and horizontal rungs with contacts and coils. That is why it is the first language taught in technical schools: an electrician reads it like a drawing. Contacts in series form an AND function and in parallel an OR.

The scan cycle

A PLC doesn’t react instantly: it reads every input, runs the whole program and then writes the outputs, over and over, within a few milliseconds. Understanding the scan explains why a very short pulse can go unnoticed, why rung order matters and what happens with a “double coil”.

Latching (seal-in)

A start button only gives a pulse; to keep the motor running, a contact of the output itself is placed in parallel with it. The start/stop circuit with a seal-in is the basis of almost every industrial control, and also of the interlock between two contactors that must never close at the same time, such as the up and down contactors of a door.

Timers and counters

TON delays switching on (staggered starts, traffic lights, star-delta) and TOF delays switching off (fans that keep cooling after the motor stops). The CTU and CTD counters count parts, cycles or batches, and comparators let you make decisions based on a timer or count value.

Safety: a hard-wired NC emergency stop

The emergency stop always uses a normally closed contact: if a wire breaks or a terminal comes loose, the machine stops instead of being left with no way to stop it. In addition, the mushroom button must cut the power through hard wiring, in series with the contactor coils or through a safety relay, without relying on the program alone: a standard PLC can fail or be left with an output stuck on. In the program you use an NO contact of that input (it is 1 when everything is fine) and, when the button is released, the machine must not restart by itself: Start has to be pressed again. IEC 60204-1 and ISO 13850 detail these requirements.

From the simulator to the real panel

The I0.0, Q0.0, M0.0, T0 and C0 addresses follow the style of many compact PLCs. Other brands use different names (for example %I0.0 or I:0/0), but the logic is the same. Before loading a program into a real machine, check the wiring diagram, the datasheets and the safety standards: this lab is educational.

Cell